The property need
The rehabilitation scope required removal of food-grade pump oil and construction residue from the reservoir interior before the next project phase.
A four-person Patriot crew operated three pressure washers across five approximately ten-hour workdays, adapting the plan as additional cleaning needs were identified.
Documented project takeaways
- Multi-day industrial interior-cleaning scope completed
- Four-person crew with three pressure washers
- Additional work requested as the rehabilitation progressed